Construction Programme Completion Target Dates
- 18 Dec 2015 - Phase 1 - High school building & high school parking
- January 2016* Occupation by Clyde Valley School
- 27 May 2016 - Phase 2a - Bus, nursery, ASN and primary vehicle drop off and parking
- May 2016* Occupation by Castlehill & Overtown primary schools
- 26 August 2016 - Phase 2b - External sports pitches and remaining paths & landscaping
Note that these dates can be varied by contractual changes.
*Occupation takes place after construction completion and the dates will be confirmed formally nearer the time.
Source: North Lanarkshire Council Website - Clyde Valley Schools Campus Page
For current progress photographs, please click here.